Western Geco – WG Vespucci

Research Survey Vessel

Man hours: 100228

October 2012 – 10 Weeks

  • Removal and re-installation of main thrusters (72 ton).
  • Installation of new server room.
  • Modification to all s/s streamer chutes.
  • Complete dry-docking program
  • Complete installation of CuNiFe cooling system.
  • New deck installations.
  • Electrical and Control system upgrades.