Dolphin Drilling – Borlette Dolphin

Drillship

Man hours: 8600

April 2014 – 3 Weeks

  • BOP Change out.
  • Windwall modifications.
  • Supply and fitting of non-return valves in the ballast system.
  • Supply, fabricate and deliver Grey Water System.
  • Supply, fabricate and deliver ROV cradle.
  • Fabricated ballast water treatment pipelines and valves and delivered to Walvis Bay.
  • Riding quad travelled with vessel from Walvis Bay to Liberia to continue work.
Tags:  
  • Dolphin Drilling – Borlette Dolphin